Authored by : Aishwarya Gowrishankar*
Citation: AIR 2019 HC, FAO(OS)(COMM) 9/2019 & CM 2239/2019
Bench: Hon'ble Justice Vibhu Bakhru, Hon'ble Justice Amit Mahajan
Title:
M/S Welspun Enterprises Ltd. … Appellant (s)
Versus
M/S NCC Ltd. … Respondent (s)
Jurisdiction: The High Court of Delhi
Laws:
The Limitation Act, 1963 The Arbitration and Conciliation Act, 1940 Section 37(1)(c) of the AC Act, 1940 Section 9, 12, 21, 27, 31, 34, 21, 27 of the AC Act, 1940 Article 8(1) of the European Directive of Mediation Section 12 of the Arbitration Act in the United Kingdom Article 137 of the Constitution of India Introduction: With cases attaining different judgments, procedures before seeking arbitration constantly change. This case of Welspun Enterprises vs. NCC Ltd. revolves around pre-arbitration clauses and their impact on the time period of claims.
Publication date and year: September, 2023
D.O.I Link: https://doi.org/10.59126/v2i4a12
Preferred Citation: Aishwarya Gowrishankar, Welspun Enterprises Ltd. vs. NCC Limited, Vol. II-IV, pg 96-102 (2023).
* AS Level - year 13 Al Diyafah High School, UAE; available at: aishwaryashankar15@gmail.com.